The Forge, Sheffield

Main Contractor:
Carillion
Client:
Unite
Sector:
Education
Package Value:
£1.8m

A time critical development of 1162 bedrooms for Sheffield’s University students.

Overlooking Sheffield United's Football stadium, the development comprised 1162 bedrooms which are spread over four blocks.

The complete package included Drylining, Partitioning, Suspended Ceilings, Fire Protection and Joinery works carried out by Horbury Building Systems Ltd, MWS Joinery Ltd and Titan Ceilings Ltd.

The partitions, drylining and suspended ceiling works were completed in 22 weeks and the joinery work was completed in just 14 weeks.

Co-ordination of the interface of all the Group companies was the key to the success of the project.